This section maintains the execution schedule for ultra high density mango plantation. The execution schedule is based on:
- Recommendations from standard literature available on UHDP
- My ability to source the required resources (Labor, Money, Time, Etc)
- My response to natural occurrences (Rain, Pests, Fungus, etc)
I shall periodically update this table to reflect work executed by date. The rationale of my actions shall be documented separately.
Table of Activities:
| Date | Activity | Labor | Material | Total Cost |
|---|---|---|---|---|
| Land Preparation | ||||
| 18th May 2013 | Sourcing of Mango Saplings |
| 40000 | |
| 6th June 2013 | Sourcing of Drip Lines | 94590 * 0.3 Transport = 1500 | 30000 | |
| 15th May 2013 | JCB Trenching Work | 700 Hrs * 70 * .5 | 24500 | |
| 8th June 2013 | FYM sourcing | 2 Truck Loads @ 7000/Load * .5 | 7000 | |
| 8th June 2013 | Fertilizer Sourcing for Basal Application | NK = 500g * 600 @ 12/KG SSP = 250g * 600 @ 8/KG MOP = 100g * 600 @ 18/KG Phorate = 10g * 600 @ 80/KG | 6900 | |
| 10th to 22nd June 2013 | Earth Work (Basal Application + Planting) | 6 ManDays * 12 days @ 175 / person (150F, 200M) | 12600 | |
| Aug | Fertigation (13:0:45) | 10KG @ 80/KG | 800 | |
| Sept | Fertigation (13:0:45) | 10KG @ 80/KG | 800 | |
| Oct | Fertigation (13:0:45) | 10KG @ 80/KG | 800 | |
| Oct | Deweeding thinking end of rainy season | 2 ManDays * 28 @ 150 / person (full time) | 8400 | |
| Nov | Deweeding | 2 ManDays * 14 @ 150 / person (full time) | 4200 | |
| Nov | Fertigation (13:0:45) | 10KG @ 80/KG | 800 | |
| Dec | Pruning & Staking | 2 ManDays * 24 @150 / person | 7200 | |
| Dec | Solid Fertilizer | Urea = 50g * 600 @ 6/kg SSP = 100g * 600 @ 8/kg MOP = 50g * 600 @ 18/kg | 1200 | |
| Jan 2014 | ||||
| Total | 145200 |